Electricity–natural gas dual energy lets a gas-heated commercial or institutional building shift most of its heating to electricity while keeping gas for the coldest weather. In Québec, it rests on three pillars: an electricity rate specific to business customers, an agreement between Hydro-Québec and Énergir, and financial assistance now administered by Énergir. Here is the state of the offer in 2026, its technical conditions and what to plan for in design.

Information verified in October 2026 with Hydro-Québec, Énergir, the Régie de l’énergie (Québec’s energy regulator), quebec.ca and Natural Resources Canada.

What is electricity–natural gas dual energy?

Electricity–natural gas dual energy is a central heating system that uses electricity as the main source and natural gas as the backup source, with the switch from one source to the other controlled automatically by the outdoor temperature. It is therefore not a peak signal sent by Hydro-Québec during an event: a temperature probe triggers the switchover.

The mechanism: a probe and a switchover temperature

According to Hydro-Québec’s 2026 Electricity Rates, the temperature probe is supplied and installed by Hydro-Québec; it tells the automatic switchover device that a change of mode is required, and fuel mode is used when the outdoor temperature is below −12°C or −15°C, depending on the climate zones defined by Hydro-Québec. Documents from Énergir and Hydro-Québec intended for partners cite Abitibi and Saguenay among the regions that switch over at −15°C.

Why a temperature rather than a grid signal? Before the Régie de l’énergie, Hydro-Québec explained that the coldest periods coincide with its highest supply needs, and that the annual peak has never occurred, in Montréal, at a temperature that was not below −12°C. Hydro-Québec also indicated that it does not rule out remotely controlled switchover in the medium term.

What share of heating shifts to electricity?

When the agreement was announced in 2021, Hydro-Québec described dual energy as using electricity as the main energy source for roughly 70% of the heating, with natural gas taking over in extreme cold. The announced objective was to reduce the natural gas consumption of participating customers by a little over 70%. These proportions are program averages: the actual share depends on the local climate, the building’s load curve and the capacity of the electric equipment installed.

The Hydro-Québec–Énergir agreement: dates, objectives and GHG contribution

The dual-energy offer stems from a 20-year collaboration agreement concluded on July 13, 2021 between Hydro-Québec and Énergir, and publicly announced on July 14, 2021. It aims at partial conversion to electricity of the heating of buildings supplied with Énergir natural gas, without adding electrical load during winter peaks.

The official objectives

  • GHG reduction: 540,000 tonnes of CO2 equivalent by 2030, according to Hydro-Québec.
  • Target customers: conversion to dual energy of 100,000 Énergir customers (residential, commercial and institutional), according to the application filed with the Régie de l’énergie.
  • Electrical peak: Hydro-Québec estimated that full electrification of these customers would add nearly 2,000 MW to peak-period demand.
  • Cost to society: savings of nearly $1.7 billion between 2022 and 2030 compared with an all-electric scenario, according to Hydro-Québec.

The GHG reduction contribution

In regulatory documents, the agreement’s financial mechanism is called the GHG reduction contribution (contribution pour la réduction des GES, or “Contribution GES”). Hydro-Québec pays Énergir an annual contribution for each customer who adopts dual energy, for 15 years from adoption, to account for Énergir’s lost revenue and to balance the rate impact between the two distributors’ customer bases. According to the Régie de l’énergie, the cumulative rate impact by 2030 of the dual-energy scenario would be 1.43% for Hydro-Québec (of which 0.55% is related to the GHG Contribution) and 0.9% for Énergir.

The regulatory path has been long. The Régie approved phase 1 (residential and the principle of the contribution) in its decision D-2022-061 of May 19, 2022, then set the dual-energy rate for the commercial and institutional customer base in decisions D-2023-068 (May 31, 2023) and D-2023-072, which sets its entry into force at June 12, 2023. Hydro-Québec states that commercial and institutional customers have had access to the offer since November 6, 2023. The GHG Contribution is also the subject of a dispute: according to Énergir, a Superior Court decision of February 16, 2024 reinstated the Régie’s initial decision, and the hearing before the Court of Appeal was scheduled for “T2-2026”. Énergir states that the offer continues to be available and that the contribution has been paid since the solution was put in place.

A first adoption period ending at the end of 2026

The first adoption period covers customers who chose dual energy between January 1, 2022 and December 31, 2026; the agreement provides that the parties may agree on the parameters of a second period, from January 1, 2027 to December 31, 2030. In its annual information form (fiscal year ended September 30, 2025), Énergir indicates that the current agreement is in force until December 31, 2026 and that the two companies have committed to begin discussions in January 2026 on extending it. For a project that will not be in service before 2027, it is prudent to confirm the conditions with Énergir at the time of signing.

As for results, Énergir reports 6,285 adoptions, all sectors combined, since the initiative was approved, and a reduction of 11,114 tonnes of CO2 equivalent for its 2025 fiscal year.

What is the dual-energy offer for commercial and institutional buildings?

For business customers, the offer combines Hydro-Québec’s small- and medium-power dual-energy rate, which applies only to electricity used for space heating, and a financial assistance program for conversion managed by Énergir. The rate and the assistance have separate conditions, which must be read separately.

The small- and medium-power dual-energy rate

This rate is covered in chapter 8 of the 2026 Electricity Rates. It applies to the annual small- or medium-power subscription of a customer who uses a compliant dual-energy system, and only to the electricity used by that system for space heating; electricity for other uses is covered by a separate subscription under Rate G, M or G9. According to an Énergir FAQ from January 2024, only buildings eligible for Rates G, M and G9 have access to the offer; large-power customers (Rate L) are excluded. Hydro-Québec accepts natural gas, propane, fuel oil or wood pellets as the backup fuel for this rate, but the financial assistance described below targets only Énergir natural gas.

Period (Electricity Rates in effect April 1, 2026)Dual-energy meter price
Heating period (October 1 to April 30), temperature ≥ −12°C or −15°C6.995¢/kWh
Heating period, temperature < −12°C or −15°C62.558¢/kWh
Heating period: demandNo billing demand
Non-heating period (May 1 to September 30)Structure equivalent to the base rate (G, M or G9, depending on the power demand)

As a benchmark, Rate G bills energy in 2026 at 12.388¢/kWh for the first 15,090 kilowatt-hours and 9.534¢/kWh for the rest, and Rate M at 6.292¢/kWh for the first 210,000 kilowatt-hours then 4.666¢/kWh, plus $18.242 per kilowatt of billing demand. For a Rate M customer, the appeal of the dual-energy rate therefore lies mostly in the absence of demand billing during the heating period, while the price below the switchover temperature is deliberately dissuasive. Hydro-Québec advertises recurring annual savings of 15% on average on energy costs; this figure is an average for the offer, not a guarantee for a given building. To understand the structure of the general rates, see our article on Hydro-Québec’s business electricity rates.

Technical conditions of the dual-energy system

Sections 8.3 and 8.4 of the 2026 Electricity Rates impose the following conditions, among others:

  • a central space heating system, designed so that electricity is the main source and a fuel is the backup source;
  • a fuel-mode capacity sufficient to supply the heat needed for the spaces concerned;
  • no simultaneous use of the two sources below the switchover temperature;
  • an automatic switchover device connected to Hydro-Québec’s probe; a customer-controlled switchover device is permitted, but only in the event of equipment failure or a power outage;
  • a post-outage recovery device, if there is one, that complies with Hydro-Québec’s requirements (operation in fuel mode only for a certain time);
  • an electrical supply not served by an off-grid network.

Metering: a separate meter with dual registers

The electricity that supplies the dual-energy system must be measured separately, using a meter capable of measuring maximum power demand. Hydro-Québec specifies that it is a dual-register meter, because two price structures apply; other uses (lighting, outlets, etc.) remain on the standard meter. According to Énergir’s FAQ, only equipment operating in dual-energy mode may be connected to the dual-energy meter, and a rooftop unit connected to this meter has all of its consumption billed at the dual-energy rate, fan included. The rate applies from the date the appropriate meter is installed, after receipt of the dual-energy conformity certificate (Attestation de conformité biénergie) signed by the customer. The customer bears the costs of verifying and bringing its system into compliance; if the distribution network must be adapted, Hydro-Québec states that this work is carried out at no cost to the customer.

What financial assistance is available to convert a building to dual energy?

Assistance for converting a commercial or institutional building now goes through a single window: Énergir’s dual-energy program, funded by Hydro-Québec, Énergir and the Québec government under the 2030 Plan for a Green Economy. This program has been in force since April 1, 2026, and its participation guide was revised on June 18, 2026.

This assistance was previously part of the ÉcoPerformance program. The ÉcoPerformance regulatory framework that came into force on July 7, 2026 then removed this component: the program’s official page states that the commercial and institutional (CI) dual-energy component has been removed from ÉcoPerformance’s regulatory framework and is now managed by Énergir. On April 10, 2026, Québec announced $163.4 million in assistance to Énergir for this program, from which more than 11,000 households and nearly 450 commercial and institutional buildings should benefit. The other ÉcoPerformance components are presented in our article on the ÉcoPerformance program, and the gas distributor’s other programs in Énergir’s grants for businesses.

Who is eligible?

  • Participants: any legally constituted business with an establishment in Québec, regardless of sector, as well as consortia, social economy enterprises (cooperatives and non-profits), sole proprietorships and recognized Indigenous communities. You must be an Énergir customer and use natural gas for space heating.
  • Buildings: commercial and institutional buildings, mixed-use buildings and residential buildings of 20 units or more. Buildings located on an industrial site, including administrative offices with a commercial purpose on that site, are excluded.
  • Existing building: heated with natural gas for at least 12 months before the application, with regular consumption mainly for space heating. A new construction may be eligible if it has access to Énergir’s network and is about to be connected to it.
  • Work: replacement of end-of-life gas appliances with the addition of electric appliances in dual-energy mode, addition of electric appliances in dual-energy mode to existing gas appliances, or a complete dual-energy system in new construction, an addition or a major renovation. The system must serve only the loads covered by the small- and medium-power dual-energy rate.

Not eligible, among other things: work completed before the application is filed, conversion of a fossil fuel other than natural gas, and replacement of a gas water heater with an electric water heater.

Simplified path or custom path

Simplified pathCustom path
For whomPreset incentive based on listed equipmentEquipment or expenses that cannot be modelled, or targeted incentive above the simplified path cap
Calculation80% × (estimated project cost − estimated baseline cost)80% × (estimated project cost − estimated baseline cost), limited to $250 per tonne of CO2 equivalent avoided over 10 years
Cap$250,000 per application and per site$3,000,000 per application; $6,000,000 per site
Engineering requirementPreliminary calculation by a professional, validated by ÉnergirProject plan signed by a member of the Ordre des ingénieurs du Québec; incentive recalculated based on actual costs

The estimated baseline cost corresponds to the cost of a scenario without dual energy: the incentive therefore covers the incremental cost of dual energy, not the total cost. Énergir reserves the right to adjust or refuse the incentive when the anticipated GHG reductions are not consistent with the program’s objectives, and may request the assumptions, thermal loads and equipment sizing.

Eligible expenses

Eligible expenses include the purchase and installation of electric or hybrid gas–electric heating appliances, the increase of electrical capacity if required, the electrical modifications for adding the Hydro-Québec meter reserved for dual-energy appliances, the upgrade of the building’s electrical system between the service mast and the panel, as well as certain related expenses (transition roof curb, aesthetic panels required by regulation, transformer for equipment operating at a voltage other than 600 V). Not eligible: natural gas equipment and its peripherals, upgrades that replace end-of-life equipment, gas connection of new buildings and, for the simplified path, internal costs.

Deadlines and commitments to respect

  • Look-back date: the application must be filed no later than 30 days after the start of work (date of the first invoice on the simplified path, of the first purchase order on the custom path).
  • Completion: 48 months after the incentive is confirmed, plus a maximum of 12 months in exceptional circumstances.
  • Rate: commitment to use the dual-energy rate for at least ten years.
  • Stacking: assistance from organizations other than Énergir, Hydro-Québec and the Québec government is not authorized.
  • Inspection: Énergir may inspect the system within 12 months of its commissioning; if the measures are not installed, commissioned or configured in accordance with the program, the incentive must be repaid.

Commercial or residential (Rate DT) dual energy: what changes?

Residential dual energy and commercial and institutional dual energy rest on the same switchover principle at −12°C or −15°C, but not on the same rate, the same metering or the same assistance. The conditions of one do not apply to the other.

ItemResidential: Rate DTCommercial and institutional: small- and medium-power dual-energy rate
Consumption coveredAll of the subscription’s consumptionOnly the dual-energy system’s electricity for space heating
MeteringSubscription meterSeparate dual-register meter; other uses on Rate G, M or G9
Energy price (April 1, 2026)5.131¢/kWh above the threshold; 30.001¢/kWh below the threshold, all year6.995¢/kWh above the threshold; 62.558¢/kWh below the threshold, October 1 to April 30
Other componentsNetwork access charge (46.154¢/day) and demand above the billing threshold ($7.266/kW)No demand billed during the heating period; base rate structure from May 1 to September 30
Simultaneous use of both sourcesProhibitedProhibited only below the switchover temperature
Manual switchoverManual device permittedOnly in the event of equipment failure or power outage
Énergir assistance (component)Fixed amounts by dwelling type (e.g., up to $7,300 for an existing forced-air house), dwellings of 19 units or fewer80% of the incremental cost, caps of $250,000 (simplified) or $6M per site (custom); CI buildings and residential buildings of 20 units or more

Two nuances deserve attention. First, the authorization of simultaneous operation above the switchover temperature is specific to the business rate: the Régie noted that the terms allow heat pumps to use fuel partly or entirely if they are not sufficient for the load, with fuel mode mandatory only below the switchover temperature. Second, for a building of 20 units or more admitted to Énergir’s commercial and institutional component, the guide only states that the rate varies depending on the type of building: the applicable electricity rate (DT or business rate) should be validated case by case with Hydro-Québec.

How does dual energy relate to peak demand management?

Dual energy removes electric heating load from the grid during the coldest hours, which coincide with Hydro-Québec’s winter peak: it is a peak management tool built into the rate rather than an on-call program. In its decision D-2023-068, the Régie said it was satisfied with Hydro-Québec’s demonstration that probe-based switchover at −12°C (or −15°C) erases demand during the most critical peak hours, which avoids the costs of new power supply.

The data presented by Hydro-Québec at the hearing qualify this finding: above a demand of 33,000 MW, dual energy provided load shedding 87% of the time, and above 35,000 MW, 98% of the time, whereas the winter 2021-2022 peak was about 43,000 MW. One intervenor, the RNCREQ, argued that about a third of peak hours are not erased by a fixed-temperature switchover. The Régie nonetheless retained the probe as a simple, proven and neutral technology.

Three practical consequences for a manager:

  • a dual-energy rate subscription cannot combine, for the same subscription, the winter credit option, the GDP Engagement and Latitude options or the additional electricity option;
  • according to Énergir’s January 2024 FAQ, the power demand management offer remains possible for the meter of the building’s other loads, but not for the dual-energy meter;
  • on the gas side, the Régie approved an amendment to Énergir’s service conditions so that the peak service surcharge does not apply to customers on Hydro-Québec’s small- and medium-power dual-energy rate.

What design and engineering elements should you plan for?

A successful dual-energy conversion rests on three engineering decisions: the installed electrical capacity relative to the switchover temperature, the control sequence between the two sources, and the capacity of the electrical service. The rate sets the rules; it guarantees neither the performance nor the profitability of an installation.

Size for the switchover temperature, not for full load

The system must be able to heat entirely with gas: fuel-mode capacity must cover the design load. On the electrical side, the Hydro-Québec and Énergir training document (revised in November 2024) recommends sizing the electric appliances to meet the building’s need down to −12°C, and no more. Its indicative example, a school consuming 50,000 m³ of gas per year, compares an electric boiler of about 300 kW for full load with about 140 kW for a dual-energy application. Oversizing increases equipment costs and electrical work with no rate benefit.

With an air-to-water or air-to-air heat pump, capacity drops in cold weather. Hydro-Québec told the Régie that standard-compressor heat pumps have a cut-off temperature of around −9°C to −12°C; between these temperatures and the switchover point, gas backup can supplement the heat pump without breaching the rate. An hourly load analysis, supported by energy modelling, makes it possible to weigh a heat pump, an electric boiler or a combination of the two.

Controls and regulation

  • Switchover signal: according to Énergir’s FAQ, only the Hydro-Québec probe signal can command the switchover; it may be sent directly to the equipment or through the building control system. The probes are supplied and installed at no cost by Hydro-Québec, but installation of the switchover system is at the customer’s expense.
  • Complete shedding: any electrical equipment connected to the dual-energy meter must be able to shed completely at the switchover temperature.
  • Sequence above −12°C: the economic benefit depends on giving priority to electricity as long as the temperature allows. For dual-energy hot-water systems, Natural Resources Canada recommends checking that the electric boiler actually delivers the power demanded and adjusting the control system sequences to maximize its use.
  • Hybrid rooftop units: according to the training document, in most models the burner and the heat pump cannot operate simultaneously; a downstream modulating electric coil can offset the heat pump’s loss of capacity down to −12°C. For variable-volume units, make sure the building control communicates with the unit’s internal controller (BACnet protocol).
  • Post-outage recovery: if a fuel-mode recovery device is provided, it must comply with Hydro-Québec’s requirements.

Electrical service and metering

Adding a separate meter may require splitting the existing service or adding one, according to Hydro-Québec’s standard E.21-10 (Blue Book). The training document also notes that several air-to-water heat pumps are supplied at 575 V, whereas Hydro-Québec’s network distributes at 600 V: a transformer may be required. These items should be integrated from the feasibility study onward, because they weigh on project cost and on the connection schedule.

Commissioning and monitoring

On the custom path, the project plan must be signed by an engineer, present the baseline scenario and the project scenario, and incorporate the relevant requirements of the ISO 14064-2 standard; after the work, a commissioning report signed by an engineer is required. Beyond compliance, monitoring of operating data is decisive: in a CanmetENERGY case study of an office building near Montréal, the electric boiler delivered on average 40% less heat than demanded, because of burnt-out heating elements. This is typically the kind of anomaly that recommissioning detects.

How ORT Énergie can support you

ORT Énergie is a Québec-based energy efficiency engineering consulting firm. For a dual-energy project, we can step in at the following stages:

  • Preliminary analysis: energy audit and modelling to estimate the heating load and the share that can be transferred to electricity above the switchover temperature;
  • Design, plans and specifications: choice of configuration (heat pump, electric boiler, hybrid unit), sizing and control sequences;
  • Financial assistance: support with the financial assistance application to Énergir;
  • Commissioning and recommissioning: verification of the switchover and sequences, then operations monitoring;
  • Peak management: analysis of the options applicable to the meter for the building’s other loads.

Dual energy can also fit within a broader approach, presented in our article on decarbonization strategies; when gas must be eliminated completely, other solutions such as geothermal can be compared on the same analytical basis.

Conclusion

In 2026, commercial and institutional dual energy rests on a technically stable framework (probe-based switchover at −12°C or −15°C, separate meter, rate with no billing demand during the heating period) and on financial assistance now consolidated at Énergir. The uncertainty mainly concerns the post-2026 period: the first adoption period of the Hydro-Québec–Énergir agreement ends on December 31, 2026. For owners considering a conversion, the priority is to size the electrical portion properly, to design control sequences that favour electricity above the switchover temperature, and to confirm the program conditions before committing any expense.

Frequently asked questions (FAQ)

At what temperature does a dual-energy system switch to natural gas?

The switch to fuel occurs when the outdoor temperature is below −12°C or −15°C, depending on the climate zone defined by Hydro-Québec. The switchover is controlled by an outdoor temperature probe supplied and installed by Hydro-Québec. Below this threshold, electricity on the dual-energy meter is billed at a very high price (62.558¢/kWh in 2026), which makes gas more advantageous.

Does the dual-energy rate apply to all the electricity in a commercial building?

No. The small- and medium-power dual-energy rate applies only to the electricity consumed by the dual-energy system for space heating, measured by a separate meter. Lighting, outlets and other uses remain on Rate G, M or G9. This is a major difference from the residential Rate DT, which applies to all consumption.

What is the maximum assistance for a business converting to dual energy?

Under Énergir’s program in force since April 1, 2026, the simplified path covers 80% of the project’s incremental cost relative to a baseline scenario, up to $250,000 per application and per site. The custom path applies the same calculation, limited to $250 per tonne of CO2 equivalent avoided over 10 years, with caps of $3M per application and $6M per site. Énergir reserves the right to modify or end the program at any time, without notice.

Is a building heated with fuel oil or propane eligible for the dual-energy offer?

Hydro-Québec’s dual-energy rate accepts natural gas, propane, fuel oil or wood pellets as the backup fuel. However, the financial assistance under Énergir’s program targets buildings heated with Énergir natural gas; conversion involving another fossil fuel is not eligible. For fuel oil and propane, you must look to other programs.

Can the heat pump and the gas boiler run at the same time?

Under the business rate, the two sources must not operate simultaneously below the switchover temperature. Above that temperature, the Régie de l’énergie noted that gas backup can supplement a heat pump whose capacity is insufficient. The residential Rate DT, for its part, prohibits any simultaneous use.

Will the dual-energy offer still be available in 2027?

The first adoption period of the Hydro-Québec–Énergir agreement ends on December 31, 2026, and the agreement provides for a possible second period from 2027 to 2030. Énergir indicated that discussions on the extension were to begin in January 2026. In the absence of an official announcement consulted in October 2026, you must confirm the conditions with Énergir before launching a project.